一、旨揭工程由「潔光國際股份有限公司」承攬,
二、本案進行綜合院館8樓露台遮陽板之拆除作業,將搭設防墜平台,使用吊車至屋頂平台,
三、施工期程為115年3月20日至5月18日,
The Terrace Canopy Removal Project for the General Building of Colleges will be undertaken by Jie Guang International Co., Ltd. from March 20 to May 18, 2026, with completion expected on or before May 18, 2026.
The project includes the dismantling of the canopy on the 8th-floor terrace. A fall-prevention platform will be erected, and a crane will be used on the rooftop to cut and remove the canopy in sections.
For safety reasons, the 2nd-floor entrance to the General Building of Colleges will be closed during the construction period. Please use the 1st-floor entrance for access. We apologize for any inconvenience caused and appreciate your understanding and cooperation.
For inquiries, please contact Ms. Wu at Ext. 63091.